ITAC Assessment: BS0144
ITAC logo
ITAC Assessment: BS0144
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Carbide Tooling
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 50,000
ft2
Annual Production 340,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $166,375 3,614,659
kWh
Electricity Demand $46,196 7,215
kW-mo/yr
Electricity Fees $13,114 -
Natural Gas $4,682 886
MMBtu
TOTAL YEARLY COSTS $230,367
RECOMMENDED SAVINGS* $11,073 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1321: Replace fossil fuel equipment with electrical equipment $2,152 $180 $(-38.0)
(-821)
kWh
- $2,190
-
MMBtu
02 2.7224: Reduce space conditioning during non-working hours $260 $159 $62
1,355
kWh
- $198
-
MMBtu
03 2.7224: Reduce space conditioning during non-working hours $405 $579 $405
8,804
kWh
- -
04 2.2514: Cover open tanks $495 $547 $416
9,040
kWh
$79
-
kW-mo/yr
-
05 2.6215: Shut off air conditioning in winter heating season $5,985 $6,222 $5,985
130,032
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,776 $452 $1,492
32,412
kWh
$284
-
kW-mo/yr
-
TOTAL RECOMMENDED $11,073 $8,139 $8,322
180,822
kWh
$363
-
kW-mo/yr
$2,388
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs