Assessment Year | 2020 |
---|---|
Principal Product | Bath Tubs |
NAICS | 326191: Plastics Plumbing Fixture Manufacturing |
SIC | 3088: Plastics Plumbing Fixtures |
Sales Range | $10 M to 50M |
# of Employees | 172 |
Plant Area |
113,000
ft2
|
Annual Production | 78,200
pieces
|
Production Hrs. Annual | 4,064
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $72,259 | 1,439,139 |
kWh
|
$0.050 | |
Electricity Demand | $18,334 | 3,769 |
kW-mo/yr
|
$4.86 | |
Electricity Fees | $3,344 | - |
|
- | |
Natural Gas | $58,197 | 12,171 |
MMBtu
|
$4.78 | |
Other Gas | $5,229 | 190 |
MMBtu
|
$27.52 | |
Waste Disposal Costs | |||||
Water Usage | $3,515 | 1,132,472 |
Tgal
|
$0.003 | |
TOTAL YEARLY COSTS | $160,878 | ||||
RECOMMENDED SAVINGS* | $37,742 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,104 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,104 | - |
$1,104
21,987
kWh
|
- | - | |
02 | 2.7314: Reduce ventilation air | $2,625 | $7,998 |
$2,625
52,274
kWh
|
- | - | |
03 | 2.4321: Upgrade obsolete equipment | $4,702 | $21,000 |
$(-527.0)
(-10,500)
kWh
|
- |
$5,229
-
MMBtu
|
|
04 | 2.7135: Install occupancy sensors | $1,055 | $1,765 |
$1,055
21,010
kWh
|
- | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $13,551 | $13,500 |
$(-366.0)
(-7,290)
kWh
|
$13,917
-
MMBtu
|
- | |
06 | 2.7292: Lower ceiling to reduce conditioned space | $14,705 | $45,023 | - |
$14,705
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $37,742 | $89,286 |
$3,891
77,481
kWh
|
$28,622
-
MMBtu
|
$5,229
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,104 | - |
$1,104
21,987
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs