Assessment Year | 2019 |
---|---|
Principal Product | Frozen Vegetables |
NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
Sales Range | $100 M to 500M |
# of Employees | 220 |
Plant Area |
465,506
ft2
|
Annual Production | 121,000,000
lb
|
Production Hrs. Annual | 4,032
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $355,306 | 18,167,800 |
kWh
|
$0.020 |
Electricity Demand | $225,419 | 43,972 |
kW-mo/yr
|
$5.13 |
Natural Gas | $417,225 | 85,551 |
MMBtu
|
$4.88 |
TOTAL YEARLY COSTS | $997,950 | |||
RECOMMENDED SAVINGS* | $37,999 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $395 | $1,259 | - | - |
$395
-
MMBtu
|
|
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $141 | $38 |
$80
3,992
kWh
|
$61
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $131 | $180 |
$131
6,532
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,199 | $1,230 |
$1,199
59,942
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,547 | $14,646 |
$4,310
212,265
kWh
|
$3,237
-
kW-mo/yr
|
- | |
06 | 2.2621: Modify refrigeration system to operate at a lower pressure | $28,587 | $13,000 |
$28,587
1,429,359
kWh
|
- | - | |
TOTAL RECOMMENDED | $37,999 | $30,353 |
$34,306
1,712,090
kWh
|
$3,298
-
kW-mo/yr
|
$395
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs