ITAC Assessment: BS0130
ITAC logo
ITAC Assessment: BS0130
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Frozen Vegetables
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $100
M
to 500
M
# of Employees 220
Plant Area 465,506
ft2
Annual Production 121,000,000
lb
Production Hrs. Annual 4,032
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $355,306 18,167,800
kWh
Electricity Demand $225,419 43,972
kW-mo/yr
Natural Gas $417,225 85,551
MMBtu
TOTAL YEARLY COSTS $997,950
RECOMMENDED SAVINGS* $37,999 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $395 $1,259 - - $395
-
MMBtu
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $141 $38 $80
3,992
kWh
$61
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $131 $180 $131
6,532
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,199 $1,230 $1,199
59,942
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $7,547 $14,646 $4,310
212,265
kWh
$3,237
-
kW-mo/yr
-
06 2.2621: Modify refrigeration system to operate at a lower pressure $28,587 $13,000 $28,587
1,429,359
kWh
- -
TOTAL RECOMMENDED $37,999 $30,353 $34,306
1,712,090
kWh
$3,298
-
kW-mo/yr
$395
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs