ITAC Assessment: BS0127
ITAC logo
ITAC Assessment: BS0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Iron Castings
NAICS 331511: Iron Foundries
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $1
M
to 5
M
# of Employees 200
Plant Area 1,194,881
ft2
Annual Production 30,000
ton
Production Hrs. Annual 5,800
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $592,761 29,803,200
kWh
Electricity Demand $465,743 91,723
kW-mo/yr
Electricity Fees $1,014 -
Natural Gas $117,232 36,635
MMBtu
Waste Disposal Costs
Water Usage $53,839 8,386
Tgal
TOTAL YEARLY COSTS $1,230,589
RECOMMENDED SAVINGS* $19,496 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7135: Install occupancy sensors $444 $240 $444
22,222
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,465 $10,665 $3,365
168,244
kWh
$1,100
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,969 $1,830 $1,296
64,794
kWh
$673
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,701 $2,200 $3,264
163,200
kWh
$2,437
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $4,941 $9,000 $1,345
67,271
kWh
$3,596
-
kW-mo/yr
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,976 $50 $1,307
65,331
kWh
$669
-
kW-mo/yr
TOTAL RECOMMENDED $19,496 $23,985 $11,021
551,062
kWh
$8,475
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs