Assessment Year | 2019 |
---|---|
Principal Product | Iron Castings |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $1 M to 5M |
# of Employees | 200 |
Plant Area |
1,194,881
ft2
|
Annual Production | 30,000
ton
|
Production Hrs. Annual | 5,800
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $592,761 | 29,803,200 |
kWh
|
$0.020 | |
Electricity Demand | $465,743 | 91,723 |
kW-mo/yr
|
$5.08 | |
Electricity Fees | $1,014 | - |
|
- | |
Natural Gas | $117,232 | 36,635 |
MMBtu
|
$3.20 | |
Waste Disposal Costs | |||||
Water Usage | $53,839 | 8,386 |
Tgal
|
$6.42 | |
TOTAL YEARLY COSTS | $1,230,589 | ||||
RECOMMENDED SAVINGS* | $19,496 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $444 | $240 |
$444
22,222
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,465 | $10,665 |
$3,365
168,244
kWh
|
$1,100
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,969 | $1,830 |
$1,296
64,794
kWh
|
$673
-
kW-mo/yr
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,701 | $2,200 |
$3,264
163,200
kWh
|
$2,437
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,941 | $9,000 |
$1,345
67,271
kWh
|
$3,596
-
kW-mo/yr
|
|
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,976 | $50 |
$1,307
65,331
kWh
|
$669
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $19,496 | $23,985 |
$11,021
551,062
kWh
|
$8,475
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs