| Assessment Year | 2019 |
|---|---|
| Principal Product | Lumber |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $100 M to 500M |
| # of Employees | 185 |
| Plant Area |
5,690,341
ft2
|
| Annual Production | 256,000
thousand feet
|
| Production Hrs. Annual | 4,807
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $905,874 | 27,380,507 |
kWh
|
$0.033 | |
| Electricity Demand | $161,835 | 49,927 |
kW-mo/yr
|
$3.24 | |
| Natural Gas | $237,930 | 59,286 |
MMBtu
|
$4.01 | |
| Waste Disposal Costs | |||||
| Water Usage | $31,968 | 13,028 |
Tgal
|
$2.45 | |
| TOTAL YEARLY COSTS | $1,337,606 | ||||
| RECOMMENDED SAVINGS* | $458,837 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,031 | $14,455 |
$8,051
243,984
kWh
|
$1,979
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,702 | $8,000 |
$4,777
144,759
kWh
|
$8,925
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,341 | $1,630 |
$2,407
72,971
kWh
|
$934
-
kW-mo/yr
|
- | |
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $882 | $15 |
$882
26,710
kWh
|
- | - | |
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $2,219 | $5,725 |
$2,219
69,432
kWh
|
- | - | |
| 06 | 2.1331: Burn a less expensive grade of fuel | $105,689 | $93,600 | - | - |
$105,689
-
MMBtu
|
|
| 07 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $322,973 | $1,002,400 |
$322,973
9,825,508
kWh
|
- | - | |
| TOTAL RECOMMENDED | $458,837 | $1,125,825 |
$341,310
10,383,364
kWh
|
$11,838
-
kW-mo/yr
|
$105,689
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs