Assessment Year | 2019 |
---|---|
Principal Product | Lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $100 M to 500M |
# of Employees | 185 |
Plant Area |
5,690,341
ft2
|
Annual Production | 256,000
thousand feet
|
Production Hrs. Annual | 4,807
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $905,874 | 27,380,507 |
kWh
|
$0.033 | |
Electricity Demand | $161,835 | 49,927 |
kW-mo/yr
|
$3.24 | |
Natural Gas | $237,930 | 59,286 |
MMBtu
|
$4.01 | |
Waste Disposal Costs | |||||
Water Usage | $31,968 | 13,028 |
Tgal
|
$2.45 | |
TOTAL YEARLY COSTS | $1,337,606 | ||||
RECOMMENDED SAVINGS* | $458,837 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,031 | $14,455 |
$8,051
243,984
kWh
|
$1,979
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,702 | $8,000 |
$4,777
144,759
kWh
|
$8,925
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,341 | $1,630 |
$2,407
72,971
kWh
|
$934
-
kW-mo/yr
|
- | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $882 | $15 |
$882
26,710
kWh
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $2,219 | $5,725 |
$2,219
69,432
kWh
|
- | - | |
06 | 2.1331: Burn a less expensive grade of fuel | $105,689 | $93,600 | - | - |
$105,689
-
MMBtu
|
|
07 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $322,973 | $1,002,400 |
$322,973
9,825,508
kWh
|
- | - | |
TOTAL RECOMMENDED | $458,837 | $1,125,825 |
$341,310
10,383,364
kWh
|
$11,838
-
kW-mo/yr
|
$105,689
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs