ITAC Assessment: BS0113
ITAC logo
ITAC Assessment: BS0113
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Trailers
NAICS 336999: All Other Transportation Equipment Manufacturing
SIC 3799: Transportation Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 181,000
ft2
Annual Production 4,500
units
Production Hrs. Annual 2,142
hrs
Location (State) Montana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,567 573,500
kWh
Electricity Demand $19,419 2,633
kW-mo/yr
Natural Gas $19,076 4,710
MMBtu
TOTAL YEARLY COSTS $74,062
RECOMMENDED SAVINGS* $6,630 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,211 $360 $727
11,724
kWh
$484
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,656 $2,640 $1,594
25,704
kWh
$1,062
-
kW-mo/yr
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,622 $100 $1,572
25,361
kWh
$1,050
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $141 $193 $141
2,269
kWh
-
TOTAL RECOMMENDED $6,630 $3,293 $4,034
65,058
kWh
$2,596
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs