Assessment Year | 2018 |
---|---|
Principal Product | Lumber |
NAICS | 333249: Other Industrial Machinery Manufacturing |
SIC | 2439: Structural Wood Members, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 165 |
Plant Area |
426,000
ft2
|
Annual Production | 94,000
thousand feet
|
Production Hrs. Annual | 4,320
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $508,570 | 15,892,800 |
kWh
|
$0.032 | |
Electricity Demand | $248,892 | 35,556 |
kW-mo/yr
|
$7.00 | |
Electricity Fees | $3,777 | - |
|
- | |
Wood | $282,720 | 339,261 |
MMBtu
|
$0.83 | |
Waste Disposal Costs | |||||
Water Usage | $613,200 | 8,760,000 |
Tgal
|
$0.070 | |
TOTAL YEARLY COSTS | $1,657,158 | ||||
RECOMMENDED SAVINGS* | $98,452 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2121: Increase amount of condensate returned | $91,034 | $31,760 | - | - |
$215
-
MMBtu
|
$90,819
-
Tgal
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,461 | $1,350 |
$3,844
120,120
kWh
|
$1,617
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $855 | $20 |
$602
18,813
kWh
|
$253
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $577 | $138 |
$577
18,042
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $525 | $2,420 |
$370
11,550
kWh
|
$155
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $98,452 | $35,688 |
$5,392
168,525
kWh
|
$2,025
-
kW-mo/yr
|
$215
-
MMBtu
|
$90,819
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs