ITAC Assessment: BS0110
ITAC logo
ITAC Assessment: BS0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Lumber
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 2439: Structural Wood Members, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 165
Plant Area 426,000
ft2
Annual Production 94,000
thousand feet
Production Hrs. Annual 4,320
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $508,570 15,892,800
kWh
Electricity Demand $248,892 35,556
kW-mo/yr
Electricity Fees $3,777 -
Wood $282,720 339,261
MMBtu
Waste Disposal Costs
Water Usage $613,200 8,760,000
Tgal
TOTAL YEARLY COSTS $1,657,158
RECOMMENDED SAVINGS* $98,452 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Water Usage Savings
01 2.2121: Increase amount of condensate returned $91,034 $31,760 - - $215
-
MMBtu
$90,819
-
Tgal
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,461 $1,350 $3,844
120,120
kWh
$1,617
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $855 $20 $602
18,813
kWh
$253
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $577 $138 $577
18,042
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $525 $2,420 $370
11,550
kWh
$155
-
kW-mo/yr
- -
TOTAL RECOMMENDED $98,452 $35,688 $5,392
168,525
kWh
$2,025
-
kW-mo/yr
$215
-
MMBtu
$90,819
-
Tgal
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs