ITAC Assessment: BS0091
ITAC logo
ITAC Assessment: BS0091
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Plywood and Veneer Wood Products
NAICS 321211: Hardwood Veneer and Plywood Manufacturing
SIC 2435: Hardwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 100,000
ft2
Annual Production 140,000
thousand feet
Production Hrs. Annual 7,488
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,811,127 39,649,729
kWh
Electricity Demand $483,526 86,631
kW-mo/yr
TOTAL YEARLY COSTS $2,294,653
RECOMMENDED SAVINGS* $96,469 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $27,778 $17,240 $22,989
499,765
kWh
$4,789
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $32,806 $39,830 $23,464
510,094
kWh
$9,342
-
kW-mo/yr
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $11,201 $240 $11,022
239,616
kWh
$179
-
kW-mo/yr
04 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $24,685 $3,100 $20,667
449,280
kWh
$4,018
-
kW-mo/yr
TOTAL RECOMMENDED $96,469 $60,410 $78,142
1,698,755
kWh
$18,327
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs