| Assessment Year | 2016 |
|---|---|
| Principal Product | Packaged Frozen Food |
| NAICS | 311412: Frozen Specialty Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 233 |
| Plant Area |
110,000
ft2
|
| Annual Production | 100,000,000
lb
|
| Production Hrs. Annual | 6,210
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $422,366 | 9,590,800 |
kWh
|
$0.044 |
| Electricity Demand | $163,175 | 20,120 |
kW-mo/yr
|
$8.11 |
| Natural Gas | $498,235 | 132,751 |
MMBtu
|
$3.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,853 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $151 | $2,312 |
$111
2,534
kWh
|
$40
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $506 | $960 |
$404
9,180
kWh
|
$102
-
kW-mo/yr
|
- | |
| 03 | 2.2211: Use optimum temperature | $419 | $116 |
$419
9,513
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $108 | $47 |
$82
1,865
kWh
|
$26
-
kW-mo/yr
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $2,122 | $220 |
$1,692
38,456
kWh
|
$430
-
kW-mo/yr
|
- | |
| 06 | 2.2521: Isolate steam lines to avoid heating air conditioned areas | $582 | $316 | - | - |
$582
-
MMBtu
|
|
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $2,966 | $15,800 | - | - |
$2,966
-
MMBtu
|
|
| TOTAL RECOMMENDED | $6,853 | $19,771 |
$2,708
61,548
kWh
|
$597
-
kW-mo/yr
|
$3,548
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs