Assessment Year | 2015 |
---|---|
Principal Product | Rock, Sand, Gravel, Concrete, and Asphalt |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
9,000,000
ft2
|
Annual Production | 1,121,215
ton
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $188,787 | 2,612,420 |
kWh
|
$0.072 |
Electricity Demand | $126,270 | 17,316 |
kW-mo/yr
|
$7.29 |
Natural Gas | $143,931 | 26,600 |
MMBtu
|
$5.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,828 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,605 | $74,360 |
$10,601
147,233
kWh
|
$3,004
-
kW-mo/yr
|
- | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $1,959 | $5,665 | - | - |
$1,959
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $223 | $702 |
$196
2,719
kWh
|
$27
-
kW-mo/yr
|
- | |
04 | 2.4131: Size electric motors for peak operating efficiency | $871 | $2,550 |
$346
4,800
kWh
|
$525
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $16,658 | $83,277 |
$11,143
154,752
kWh
|
$3,556
-
kW-mo/yr
|
$1,959
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,828 | $75,062 |
$10,797
149,952
kWh
|
$3,031
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs