ITAC Assessment: BS0045
ITAC logo
ITAC Assessment: BS0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Frozen Seafood
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 20,000
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 2,220
hrs
Location (State) Alaska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $457,865 3,224,000
kWh
Electricity Demand $51,703 9,184
kW-mo/yr
Electricity Fees $9,100 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,441 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.2511: Insulate bare equipment $6,415 $10,400 $5,402
38,040
kWh
$1,013
-
kW-mo/yr
-
02 2.2515: Use optimum thickness insulation $1,553 $2,600 $1,553
10,936
kWh
- -
03 2.8123: Pay utility bills on time $7,864 $122 - - $7,864
04 2.4231: Reduce the pressure of compressed air to the minimum required $986 $1,373 $784
5,520
kWh
$203
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,833 $5,036 $1,671
11,767
kWh
$162
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,790 $13,052 $3,121
21,978
kWh
$669
-
kW-mo/yr
-
TOTAL RECOMMENDED $22,441 $32,583 $12,531
88,241
kWh
$2,047
-
kW-mo/yr
$7,864
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs