Assessment Year | 2014 |
---|---|
Principal Product | Sewage Treatment Plant |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 34 |
Plant Area |
48,000
ft2
|
Annual Production | 16,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $496,804 | 15,693,503 |
kWh
|
$0.032 |
Electricity Demand | $140,537 | 27,391 |
kW-mo/yr
|
$5.13 |
Electricity Fees | $160,598 | - |
|
- |
Natural Gas | $37,676 | 5,581 |
MMBtu
|
$6.75 |
Fuel Oil #2 | $35,902 | 1,322 |
MMBtu
|
$27.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $101,786 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Gas Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8226: Increase efficiency of trucks | $19,366 | $24,000 | - | - | - |
$35,902
-
MMBtu
|
$(-16,536.0)
-
MMBtu
|
|
02 | 2.1336: Install equipment to utilize waste fuel | $57,736 | $307,920 |
$36,346
938,700
kWh
|
$4,767
-
kW-mo/yr
|
$16,623
-
MMBtu
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,130 | $3,375 |
$10,583
273,312
kWh
|
$2,547
-
kW-mo/yr
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $275 | $29 |
$275
7,092
kWh
|
- | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,677 | $726 | - | - |
$1,677
-
MMBtu
|
- | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $9,602 | $33,371 | - | - |
$9,602
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $101,786 | $369,421 |
$47,204
1,219,104
kWh
|
$7,314
-
kW-mo/yr
|
$27,902
-
MMBtu
|
$35,902
-
MMBtu
|
$(-16,536.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs