ITAC Assessment: BS0025
ITAC logo
ITAC Assessment: BS0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Commercial Laundry and Dry-cleaing Products
NAICS 333318: Other Commercial and Service Industry Machinery Manufacturing
SIC 3582: Commercial Laundry, Drycleaning, and Pressing Machines
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 60,000
ft2
Annual Production 144
pieces
Production Hrs. Annual 2,400
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,975 521,200
kWh
Electricity Demand $16,652 2,514
kW-mo/yr
Natural Gas $19,007 2,679
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,979 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,335 $1,104 - $6,335
-
kW-mo/yr
-
02 2.7243: Improve air circulation with destratification fans / other methods $3,537 $6,138 $(-178.0)
(-2,376)
kWh
- $3,715
-
MMBtu
03 2.7135: Install occupancy sensors $626 $495 $626
8,349
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $208 $1,211 $140
1,864
kWh
$68
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $444 $15 $239
3,185
kWh
$205
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $829 $977 $829
11,050
kWh
- -
TOTAL RECOMMENDED $11,979 $9,940 $1,656
22,072
kWh
$6,608
-
kW-mo/yr
$3,715
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs