ITAC Assessment: BD0475
ITAC logo
ITAC Assessment: BD0475
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Tracks and springs for overhead doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 73
Plant Area 272,000
ft2
Annual Production 68,325
pieces
Production Hrs. Annual 4,871
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $71,141 1,248,848
kWh
Electricity Demand $17,105 3,371
kW-mo/yr
Electricity Fees $2,526 -
Natural Gas $69,363 10,528
MMBtu
LPG $13,356 761
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,168 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,025

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.1221: Replace obsolete burners with more efficient ones $10,372 $15,000 - - $10,372
-
MMBtu
- - - - -
02 2.8227: Adjust / maintain fork lift trucks for most efficient operation $6,954 $18,000 $(-6,402.0)
(-112,320)
kWh
- - $13,356
-
MMBtu
- - - -
03 2.2437: Recover waste heat from equipment $7,287 $9,000 $(-370.0)
(-6,495)
kWh
$(-81.0)
-
kW-mo/yr
$7,738
-
MMBtu
- - - - -
04 2.4133: Use most efficient type of electric motors $3,266 $4,390 $2,679
47,008
kWh
$587
-
kW-mo/yr
- - - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,317 $600 $1,859
32,617
kWh
$458
-
kW-mo/yr
- - - - - -
06 2.7135: Install occupancy sensors $1,791 $900 $1,270
22,276
kWh
$521
-
kW-mo/yr
- - - - - -
07 2.4314: Use synthetic lubricant $1,663 $600 $1,359
23,848
kWh
$304
-
kW-mo/yr
- - - - - -
08 2.7134: Use photocell controls $1,206 $750 $660
11,571
kWh
$297
-
kW-mo/yr
- - $187 - $62 -
09 2.4221: Install compressor air intakes in coolest locations $1,155 $615 $946
16,588
kWh
$209
-
kW-mo/yr
- - - - - -
10 2.7111: Reduce illumination to minimum necessary levels $779 $198 $639
11,213
kWh
$140
-
kW-mo/yr
- - - - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $456 $375 $247
4,327
kWh
$30
-
kW-mo/yr
- - $75 - $104 -
12 2.4231: Reduce the pressure of compressed air to the minimum required $363 $20 $298
5,232
kWh
$65
-
kW-mo/yr
- - - - - -
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $131 $150 $93
1,626
kWh
$38
-
kW-mo/yr
- - - - - -
14 3.2121: Convert to electrostatic powder coating $28,428 $90,000 - - $(-1,819.0)
-
MMBtu
- $14,613 $15,634 - -
15 4.322: Eliminate old stock and modify inventory control $2,000 $500 - - - - - - - $2,000
TOTAL RECOMMENDED $68,168 $141,098 $3,278
57,491
kWh
$2,568
-
kW-mo/yr
$16,291
-
MMBtu
$13,356
-
MMBtu
$14,875 $15,634 $166 $2,000
TOTAL IMPLEMENTED $8,025 $5,788 $6,536
114,686
kWh
$1,489
-
kW-mo/yr
- - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs