ITAC Assessment: BD0471
ITAC logo
ITAC Assessment: BD0471
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Rolling overhead steel doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $5
M
to 10
M
# of Employees 51
Plant Area 73,500
ft2
Annual Production 5,000
pieces
Production Hrs. Annual 4,871
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,940 839,299
kWh
Electricity Demand $11,526 2,268
kW-mo/yr
Electricity Fees $1,693 -
Natural Gas $49,900 7,453
MMBtu
LPG $3,609 206
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $204,838 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $88,132

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7221: Lower temperature during the winter season and vice-versa $18,915 $20 - - $18,915
-
MMBtu
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,951 $7,711 $2,420
42,394
kWh
$531
-
kW-mo/yr
- - - - -
03 2.8227: Adjust / maintain fork lift trucks for most efficient operation $2,184 $6,000 $(-1,425.0)
(-24,960)
kWh
- - $3,609
-
MMBtu
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,732 $500 $1,421
24,885
kWh
$311
-
kW-mo/yr
- - - - -
05 2.7135: Install occupancy sensors $888 $450 $723
12,667
kWh
$165
-
kW-mo/yr
- - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $417 $300 $342
5,996
kWh
$75
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $245 $225 $133
2,330
kWh
$16
-
kW-mo/yr
- - $40 - $56
08 2.4231: Reduce the pressure of compressed air to the minimum required $356 $20 $292
5,106
kWh
$64
-
kW-mo/yr
- - - - -
09 3.1172: Revise raw material specs $90,750 $7,000 - - - - - $90,750 -
10 3.2123: Convert to high volume low pressure (hvlp) paint guns $86,400 $1,050 - - - - - $86,400 -
TOTAL RECOMMENDED $204,838 $23,276 $3,906
68,418
kWh
$1,162
-
kW-mo/yr
$18,915
-
MMBtu
$3,609
-
MMBtu
$40 $177,150 $56
TOTAL IMPLEMENTED $88,132 $1,550 $1,421
24,885
kWh
$311
-
kW-mo/yr
- - - $86,400 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs