| Assessment Year | 2014 |
|---|---|
| Principal Product | Industrial Hose |
| NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
| SIC | 3052: Rubber and Plastics Hose and Belting |
| Sales Range | $100 M to 500M |
| # of Employees | 240 |
| Plant Area |
465,000
ft2
|
| Annual Production | 60,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $860,170 | 20,974,866 |
kWh
|
$0.041 |
| Electricity Demand | $52,939 | 40,395 |
kW-mo/yr
|
$1.31 |
| Electricity Fees | $33,097 | - |
|
- |
| Natural Gas | $306,915 | 70,168 |
MMBtu
|
$4.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,547 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $16,957 | $8,000 |
$(-235.0)
(-5,840)
kWh
|
$(-8.0)
-
kW-mo/yr
|
$17,200
-
MMBtu
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,866 | $17,640 |
$4,130
102,492
kWh
|
$368
-
kW-mo/yr
|
- | $263 | $105 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $724 | $600 |
$295
7,323
kWh
|
$13
-
kW-mo/yr
|
- | $86 | $330 | |
| TOTAL RECOMMENDED | $22,547 | $26,240 |
$4,190
103,975
kWh
|
$373
-
kW-mo/yr
|
$17,200
-
MMBtu
|
$349 | $435 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs