Assessment Year | 2013 |
---|---|
Principal Product | Steel and iron work for repair and construction of locks and dams |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
75,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,930 | 1,288,864 |
kWh
|
$0.042 |
Electricity Demand | $29,986 | 3,725 |
kW-mo/yr
|
$8.05 |
Electricity Fees | $240 | - |
|
- |
Natural Gas | $8,694 | 1,210 |
MMBtu
|
$7.18 |
LPG | $1,062 | 52 |
MMBtu
|
$20.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,879 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,266 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,612 | $12,980 |
$1,912
45,752
kWh
|
$1,700
-
kW-mo/yr
|
- | - | - | |
02 | 2.7134: Use photocell controls | $1,708 | $500 |
$533
12,754
kWh
|
$790
-
kW-mo/yr
|
- | $96 | $289 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $654 | $730 |
$292
6,990
kWh
|
$77
-
kW-mo/yr
|
- | $121 | $164 | |
04 | 2.7231: Use radiant heater for spot heating | $618 | $2,100 | - | - |
$618
-
MMBtu
|
- | - | |
05 | 2.7135: Install occupancy sensors | $287 | $250 |
$152
3,636
kWh
|
$135
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $6,879 | $16,560 |
$2,889
69,132
kWh
|
$2,702
-
kW-mo/yr
|
$618
-
MMBtu
|
$217 | $453 | ||
TOTAL IMPLEMENTED | $4,266 | $13,710 |
$2,204
52,742
kWh
|
$1,777
-
kW-mo/yr
|
- | $121 | $164 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs