Assessment Year | 2022 |
---|---|
Principal Product | Spice Blends and Salad Dressings |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
300,000
ft2
|
Annual Production | 10,000,000
units
|
Production Hrs. Annual | 6,200
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $194,666 | 8,353,090 |
kWh
|
$0.023 | |
Electricity Demand | $120,136 | 17,212 |
kW-mo/yr
|
$6.98 | |
Electricity Fees | $483,744 | - |
|
- | |
Natural Gas | $229,887 | 49,173 |
MMBtu
|
$4.68 | |
Waste Disposal Costs | |||||
Water Usage | $69,643 | 31,015 |
Tgal
|
$2.25 | |
Water Disposal | $362,567 | 24,068 |
Tgal
|
$15.06 | |
TOTAL YEARLY COSTS | $1,460,643 | ||||
RECOMMENDED SAVINGS* | $116,313 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $111,877 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $21,858 | $44,939 |
$13,448
584,716
kWh
|
$8,410
-
kW-mo/yr
|
- | - | - | |
02 | 2.2121: Increase amount of condensate returned | $11,758 | $1,342 | - | - |
$11,758
-
MMBtu
|
- | - | |
03 | 2.1222: Install turbulators | $6,811 | $7,500 | - | - |
$6,811
-
MMBtu
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,918 | $756 |
$4,918
213,841
kWh
|
- | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,345 | - |
$1,345
58,486
kWh
|
- | - | - | - | |
06 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $45,977 | - | - | - | - | - | $45,977 | |
07 | 4.661: Level zero – install control systems for existing equipment | $19,210 | $10,000 |
$19,210
835,209
kWh
|
- | - | - | - | |
08 | 4.611: Begin a practice of predictive / preventative maintenance | $4,436 | $448 |
$2,255
98,024
kWh
|
- | - |
$2,181
-
Tgal
|
- | |
TOTAL RECOMMENDED | $116,313 | $64,985 |
$41,176
1,790,276
kWh
|
$8,410
-
kW-mo/yr
|
$18,569
-
MMBtu
|
$2,181
-
Tgal
|
$45,977 | ||
TOTAL IMPLEMENTED | $111,877 | $64,537 |
$38,921
1,692,252
kWh
|
$8,410
-
kW-mo/yr
|
$18,569
-
MMBtu
|
- | $45,977 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs