ITAC Assessment: BD0400
ITAC logo
ITAC Assessment: BD0400
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Low carbon steel balls
NAICS 332991: Ball and Roller Bearing Manufacturing
SIC 3562: Ball and Roller Bearings
Sales Range $5
M
to 10
M
# of Employees 15
Plant Area 90,000
ft2
Annual Production 120,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,737 1,961,477
kWh
Electricity Demand $25,963 4,334
kW-mo/yr
Electricity Fees $12,216 -
Natural Gas $218,989 47,350
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $81,721 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,744

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $27,912 $30,000 $(-1,592.0)
(-28,080)
kWh
$(-431.0)
-
kW-mo/yr
$29,935
-
MMBtu
02 2.1221: Replace obsolete burners with more efficient ones $15,065 $27,000 - - $15,065
-
MMBtu
03 2.7231: Use radiant heater for spot heating $12,072 $12,600 - - $12,072
-
MMBtu
04 2.4231: Reduce the pressure of compressed air to the minimum required $7,389 $20 $6,141
108,307
kWh
$1,248
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,217 $1,600 $5,999
105,800
kWh
$1,218
-
kW-mo/yr
-
06 2.4133: Use most efficient type of electric motors $6,214 $10,450 $5,165
91,094
kWh
$1,049
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,602 $2,039 $2,993
52,839
kWh
$609
-
kW-mo/yr
-
08 2.7135: Install occupancy sensors $2,250 $1,058 $1,870
32,979
kWh
$380
-
kW-mo/yr
-
TOTAL RECOMMENDED $81,721 $84,767 $20,576
362,939
kWh
$4,073
-
kW-mo/yr
$57,072
-
MMBtu
TOTAL IMPLEMENTED $38,744 $27,767 $22,168
391,019
kWh
$4,504
-
kW-mo/yr
$12,072
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs