ITAC Assessment: BD0392
ITAC logo
ITAC Assessment: BD0392
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Truck Bumpers and Chasis Stampings
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 64
Plant Area 105,000
ft2
Annual Production 80,000
pieces
Production Hrs. Annual 3,744
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $110,942 1,402,548
kWh
Electricity Demand $35,150 5,788
kW-mo/yr
Electricity Fees $9,959 -
Natural Gas $32,548 4,268
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $126,598 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,856

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7231: Use radiant heater for spot heating $9,888 $5,500 $386
6,282
kWh
$173
-
kW-mo/yr
$9,329
-
MMBtu
- - -
02 2.9114: Use solar heat to make electricty $20,276 $73,000 $12,992
164,250
kWh
$7,284
-
kW-mo/yr
- - - -
03 2.7212: Install or upgrade insulation on hvac distribution systems $6,856 $55,000 $4,428
72,000
kWh
$2,428
-
kW-mo/yr
- - - -
04 2.4133: Use most efficient type of electric motors $3,087 $7,610 $2,609
32,978
kWh
$478
-
kW-mo/yr
- - - -
05 2.4226: Use / purchase optimum sized compressor $1,781 $3,500 $1,374
22,344
kWh
$407
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,411 $1,001 $1,307
16,529
kWh
$104
-
kW-mo/yr
- - - -
07 2.7135: Install occupancy sensors $1,030 $1,000 $700
11,379
kWh
$330
-
kW-mo/yr
- - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $419 $10 $319
5,180
kWh
$100
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $241 $250 $164
2,663
kWh
$22
-
kW-mo/yr
- $23 $32 -
10 3.4151: Minimize water usage $1,525 $1,800 - - - - - $1,525
-
Tgal
11 4.453: Reschedule breaks to allow for continuous production $67,284 $10 $2,484
40,384
kWh
- - $64,800 - -
12 4.611: Begin a practice of predictive / preventative maintenance $12,800 $1,600 - - - $12,800 - -
TOTAL RECOMMENDED $126,598 $150,281 $26,763
373,989
kWh
$11,326
-
kW-mo/yr
$9,329
-
MMBtu
$77,623 $32 $1,525
-
Tgal
TOTAL IMPLEMENTED $21,856 $60,110 $6,121
99,524
kWh
$2,935
-
kW-mo/yr
- $12,800 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs