ITAC Assessment: BD0382
ITAC logo
ITAC Assessment: BD0382
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Escalators
NAICS 333921: Elevator and Moving Stairway Manufacturing
SIC 3534: Elevators and Moving Stairways
Sales Range less than $500
k
# of Employees 110
Plant Area 206,667
ft2
Annual Production 116
pieces
Production Hrs. Annual 3,536
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,361 1,707,450
kWh
Electricity Demand $37,235 5,681
kW-mo/yr
Electricity Fees $(-962.0) -
Natural Gas $97,660 13,764
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,605 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,269

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $17,174 $20,735 $10,544
275,313
kWh
$6,120
-
kW-mo/yr
- - $468 $42
02 2.1221: Replace obsolete burners with more efficient ones $3,316 $3,200 - - $3,316
-
MMBtu
- - -
03 2.2442: Preheat combustion air with waste heat $2,368 $2,000 $(-33.0)
(-867)
kWh
$(-39.0)
-
kW-mo/yr
$2,440
-
MMBtu
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $323 $442 $166
4,327
kWh
$39
-
kW-mo/yr
- - $62 $56
05 2.7135: Install occupancy sensors $244 $300 $134
3,497
kWh
$110
-
kW-mo/yr
- - - -
06 3.5316: Contract a wood pallet recycling company $1,020 $360 - - - $1,020
-
lb
- -
07 4.213: Purchase material from supplier in customized packaging $1,160 $160 - - - - $1,160 -
TOTAL RECOMMENDED $25,605 $27,197 $10,811
282,270
kWh
$6,230
-
kW-mo/yr
$5,756
-
MMBtu
$1,020
-
lb
$1,690 $98
TOTAL IMPLEMENTED $21,269 $23,637 $10,811
282,270
kWh
$6,230
-
kW-mo/yr
$2,440
-
MMBtu
- $1,690 $98
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs