ITAC Assessment: BD0337
ITAC logo
ITAC Assessment: BD0337
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Trusses,sheet metal for wall and roof covering
NAICS 321214: Truss Manufacturing
SIC 2439: Structural Wood Members, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 314,524
ft2
Annual Production 40,000
ton
Production Hrs. Annual 2,600
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,236 568,906
kWh
Electricity Demand $4,392 317
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,590 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,425

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $927 $1,115 $491
8,420
kWh
$436
-
kW-mo/yr
- -
02 2.7111: Reduce illumination to minimum necessary levels $14,425 $480 $7,181
123,188
kWh
$6,373
-
kW-mo/yr
$268 $603
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,084 $2,150 $716
12,275
kWh
$1,269
-
kW-mo/yr
$13 $86
04 2.4314: Use synthetic lubricant $228 $601 $109
1,862
kWh
$119
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $926 $2 $439
7,529
kWh
$487
-
kW-mo/yr
- -
TOTAL RECOMMENDED $18,590 $4,348 $8,936
153,274
kWh
$8,684
-
kW-mo/yr
$281 $689
TOTAL IMPLEMENTED $14,425 $480 $7,181
123,188
kWh
$6,373
-
kW-mo/yr
$268 $603
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs