Assessment Year | 2007 |
---|---|
Principal Product | paperboard |
NAICS | 322121: Paper (except Newsprint) Mills |
SIC | 2621: Paper Mills |
Sales Range | less than $500 k |
# of Employees | 48 |
Plant Area |
53,125
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,712
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $802,718 | 19,095,675 |
kWh
|
$0.042 |
Natural Gas | $99,865 | 252,295 |
MMBtu
|
$0.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $50,568 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $668 | $450 |
$667
15,874
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $460 | $650 |
$459
7,323
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,449 | $4,115 |
$5,448
129,722
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $7,742 | $42,500 |
$7,741
184,301
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,075 | $20,500 |
$9,074
216,040
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $9,125 | $1,200 |
$9,125
714
kWh
|
- | - | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $14,867 | $5,500 | - | - | - |
$14,867
-
lb
|
- | |
08 | 4.454: Modify startup/shutdown times | $2,400 | $7,000 | - | - | - | - | $2,400 | |
09 | 3.5311: Recover and reuse waste material | $512 | - | - | - | - |
$512
-
lb
|
- | |
10 | 2.2135: Repair and eliminate steam leaks | $270 | $150 | - | - |
$270
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $50,568 | $82,065 |
$32,514
553,974
kWh
|
$5
-
kW-mo/yr
|
$270
-
MMBtu
|
$15,379
-
lb
|
$2,400 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs