| Assessment Year | 2006 |
|---|---|
| Principal Product | engine block |
| NAICS | 331511: Iron Foundries |
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | n/a |
| # of Employees | 490 |
| Plant Area |
200,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,413,361 | 23,446,660 |
kWh
|
$0.060 |
| Natural Gas | $143,844 | 28,769 |
MMBtu
|
$5.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $408,544 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $270,665 | $95,987 |
$270,664
4,488,619
kWh
|
$1
-
kW-mo/yr
|
|
| 02 | 2.7124: Make a practice of turning off lights when not needed | $21,566 | - |
$21,565
357,627
kWh
|
$1
-
kW-mo/yr
|
|
| 03 | 2.7135: Install occupancy sensors | $15,542 | $29,010 |
$15,542
246,706
kWh
|
- | |
| 04 | 2.7135: Install occupancy sensors | $6,317 | $2,700 |
$6,317
100,278
kWh
|
- | |
| 05 | 2.4314: Use synthetic lubricant | $62,721 | - |
$62,721
1,161,495
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,775 | $500 |
$1,775
24,172
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $21,100 | $50,560 |
$21,100
334,921
kWh
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,858 | $8,520 |
$8,858
146,854
kWh
|
- | |
| TOTAL RECOMMENDED | $408,544 | $187,277 |
$408,542
6,860,672
kWh
|
$2
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs