ITAC Assessment: BD0272
ITAC logo
ITAC Assessment: BD0272
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Tractor Frames and Assorted Components
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 702
Plant Area 270,000
ft2
Annual Production 4,619,925
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $300,099 10,763,924
kWh
Electricity Demand $194,457 21,820
kW-mo/yr
Electricity Fees $19,263 -
Natural Gas $223,501 32,150
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $339,453 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $290,570

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2437: Recover waste heat from equipment $42,617 $1,000 - - $42,617
-
MMBtu
- - - - -
02 2.7231: Use radiant heater for spot heating $22,780 $43,400 - - $22,780
-
MMBtu
- - - - -
03 2.2437: Recover waste heat from equipment $18,914 $1,000 - - $18,914
-
MMBtu
- - - - -
04 2.2437: Recover waste heat from equipment $13,459 $1,260 - - $13,459
-
MMBtu
- - - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $7,568 $4,325 $5,265
188,697
kWh
$2,303
-
kW-mo/yr
- - - - - -
06 2.2531: Re-size charging openings or add movable cover or door $5,880 $20,000 - - $1,966
-
MMBtu
- - $3,914 - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,875 $1,700 $4,086
146,499
kWh
$1,789
-
kW-mo/yr
- - - - - -
08 2.7134: Use photocell controls $3,196 $2,500 $978
35,040
kWh
$642
-
kW-mo/yr
- - - $87 - $1,489
09 2.2515: Use optimum thickness insulation $1,383 $1,520 $371
12,658
kWh
- $1,012
-
MMBtu
- - - - -
10 2.7135: Install occupancy sensors $784 $1,500 $199
7,170
kWh
$585
-
kW-mo/yr
- - - - - -
11 2.2437: Recover waste heat from equipment $448 $650 - - $448
-
MMBtu
- - - - -
12 3.5315: Lease / purchase baler; sell cardboard to recycler $36,771 $7,140 - - - - $36,771
-
lb
- - -
13 3.5316: Contract a wood pallet recycling company $16,640 $140 - - - - $16,640
-
lb
- - -
14 3.4111: Use closed cycle process to minimize waste water production $14,414 $590 - - - $14,414
-
Tgal
- - - -
15 3.1163: Use plastic pallets instead of wood $11,370 $9,000 - - - - $11,370
-
lb
- - -
16 4.422: Utilize outside contracting $57,614 $200 - - - - - - $57,614 -
17 4.513: Re-arrange equipment layout to reduce labor costs $59,000 $15,000 - - - - - - $59,000 -
18 4.821: Pay bills on time to avoid late fees $20,740 - - - - - - - $20,740 -
TOTAL RECOMMENDED $339,453 $110,925 $10,899
390,064
kWh
$5,319
-
kW-mo/yr
$101,196
-
MMBtu
$14,414
-
Tgal
$64,781
-
lb
$4,001 $137,354 $1,489
TOTAL IMPLEMENTED $290,570 $62,005 $9,351
335,196
kWh
$4,092
-
kW-mo/yr
$77,404
-
MMBtu
$14,414
-
Tgal
$64,781
-
lb
$3,914 $116,614 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs