ITAC Assessment: BD0226
ITAC logo
ITAC Assessment: BD0226
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Gray and Ductile Iron Castings
NAICS 331511: Iron Foundries
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 210,000
ft2
Annual Production 7,000
ton
Production Hrs. Annual 5,382
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $140,813 2,378,005
kWh
Electricity Demand $29,455 9,541
kW-mo/yr
Natural Gas $70,967 6,077
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,868 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $73,478

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7231: Use radiant heater for spot heating $17,147 $11,000 - - $17,147
-
MMBtu
- - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,838 $1,200 $7,920
132,870
kWh
$918
-
kW-mo/yr
- - - - - -
03 2.4314: Use synthetic lubricant $1,169 $500 $1,048
17,585
kWh
$121
-
kW-mo/yr
- - - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $740 - $663
11,137
kWh
$77
-
kW-mo/yr
- - - - - -
05 2.4221: Install compressor air intakes in coolest locations $545 $1,250 $489
8,207
kWh
$56
-
kW-mo/yr
- - - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $74 $290 $198
3,329
kWh
$14
-
kW-mo/yr
- - $(-58.0) - $(-80.0) -
07 3.5221: Recycle casting sand $9,750 $1,000 - - - $9,750
-
lb
- - - -
08 3.5316: Contract a wood pallet recycling company $28,125 $1,000 - - - - - - - $28,125
09 4.447: Automate payroll system $25,480 $2,500 - - - - - $25,480 - -
TOTAL RECOMMENDED $91,868 $18,740 $10,318
173,128
kWh
$1,186
-
kW-mo/yr
$17,147
-
MMBtu
$9,750
-
lb
$(-58.0) $25,480 $(-80.0) $28,125
TOTAL IMPLEMENTED $73,478 $6,950 $9,072
152,214
kWh
$1,051
-
kW-mo/yr
- $9,750
-
lb
- $25,480 - $28,125
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs