Assessment Year | 2003 |
---|---|
Principal Product | Enclosures for Generators and Generator Controls |
NAICS | 335313: Switchgear and Switchboard Apparatus Manufacturing |
SIC | 3448: Prefabricated Metal Buildings and Components |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
70,000
ft2
|
Annual Production | 100
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $18,319 | 268,722 |
kWh
|
$0.068 |
Electricity Demand | $3,770 | 1,578 |
kW-mo/yr
|
$2.39 |
Electricity Fees | $2,340 | - |
|
- |
Natural Gas | $9,266 | 1,590 |
MMBtu
|
$5.83 |
Fuel Oil #2 | $9,000 | 1,380 |
MMBtu
|
$6.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,759 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $3,792 | $10,000 |
$18,319
268,722
kWh
|
$3,773
-
kW-mo/yr
|
$(-15,613.0)
-
MMBtu
|
- | - | $(-2,687.0) | - | - | - | |
02 | 2.7135: Install occupancy sensors | $1,196 | $2,100 |
$962
14,110
kWh
|
$234
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,618 | $5,072 |
$3,982
51,252
kWh
|
$487
-
kW-mo/yr
|
- |
$(-2,851.0)
-
gal
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $724 | $3,630 |
$701
10,284
kWh
|
$126
-
kW-mo/yr
|
- | - | - | $(-34.0) | - | $(-69.0) | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $873 | $300 |
$740
10,834
kWh
|
$133
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $439 | $2,280 |
$465
6,809
kWh
|
$15
-
kW-mo/yr
|
- | - | - | $(-41.0) | - | - | - | |
07 | 2.7122: Disconnect ballasts | $442 | $60 |
$358
5,242
kWh
|
$64
-
kW-mo/yr
|
- | - | - | $9 | - | $11 | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $338 | $270 |
$204
2,996
kWh
|
$10
-
kW-mo/yr
|
- | - | - | $52 | - | $72 | - | |
09 | 2.4314: Use synthetic lubricant | $240 | $350 |
$210
3,075
kWh
|
$30
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
10 | 2.4133: Use most efficient type of electric motors | $224 | $1,000 |
$197
2,886
kWh
|
$27
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
11 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $7,920 | $2,200 | - | - | - |
$7,920
-
gal
|
- | - | - | - | - | |
12 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $3,180 | $500 | - | - | - | - |
$3,180
-
lb
|
- | - | - | - | |
13 | 3.5316: Contract a wood pallet recycling company | $400 | $120 | - | - | - | - |
$400
-
lb
|
- | - | - | - | |
14 | 2.3137: Use power during off-peak periods | $3,393 | $4,000 | - | - | - | - | - | - | $3,393 | - | - | |
15 | 4.447: Automate payroll system | $2,080 | $2,500 | - | - | - | - | - | - | - | - | $2,080 | |
16 | 4.652: Replace existing equipment with more suitable substitutes | $900 | $300 | - | - | - | - | - | - | - | - | $900 | |
TOTAL RECOMMENDED | $27,759 | $34,682 |
$26,138
376,210
kWh
|
$4,899
-
kW-mo/yr
|
$(-15,613.0)
-
MMBtu
|
$5,069
-
gal
|
$3,580
-
lb
|
$(-2,701.0) | $3,393 | $14 | $2,980 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs