Assessment Year | 2001 |
---|---|
Principal Product | Industrial Processing Screens |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $5 M to 10M |
# of Employees | 48 |
Plant Area |
32,000
ft2
|
Annual Production | 4,029
pieces
|
Production Hrs. Annual | 5,720
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,361 | 430,400 |
kWh
|
$0.068 |
Electricity Demand | $4,008 | 1,603 |
kW-mo/yr
|
$2.50 |
Electricity Fees | $905 | - |
|
- |
Natural Gas | $6,807 | 1,493 |
MMBtu
|
$4.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,184 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $848 | $825 |
$766
11,225
kWh
|
$82
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.2136: Install / repair insulation on steam lines | $529 | $2,000 | - | - |
$529
-
MMBtu
|
- | - | - | |
03 | 2.4314: Use synthetic lubricant | $254 | $500 |
$236
3,456
kWh
|
$18
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $127 | - |
$118
1,728
kWh
|
$9
-
kW-mo/yr
|
- | - | - | - | |
05 | 3.5217: Reuse / recycle/ sell paper products | $784 | $1,000 | - | - | - |
$784
-
lb
|
- | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,142 | $1,500 | - | - | - |
$2,142
-
lb
|
- | - | |
07 | 4.447: Automate payroll system | $4,160 | $3,000 | - | - | - | - | $4,160 | - | |
08 | 3.5316: Contract a wood pallet recycling company | $1,340 | $480 | - | - | - | - | - | $1,340 | |
TOTAL RECOMMENDED | $10,184 | $9,305 |
$1,120
16,409
kWh
|
$109
-
kW-mo/yr
|
$529
-
MMBtu
|
$2,926
-
lb
|
$4,160 | $1,340 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs