ITAC Assessment: BD0172
ITAC logo
ITAC Assessment: BD0172
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Promotional Stamps
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $5
M
to 10
M
# of Employees 20
Plant Area 54,000
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 2,216
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $143,735 2,157,093
kWh
Electricity Demand $24,000 10,852
kW-mo/yr
Electricity Fees $180 -
Natural Gas $30,496 6,414
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $87,351 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $1,601 $4,250 $1,331
19,930
kWh
$270
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,429 $600 $1,211
18,171
kWh
$218
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $771 $1,425 $638
9,672
kWh
$133
-
kW-mo/yr
- - -
04 2.2437: Recover waste heat from equipment $493 $500 - - $493
-
MMBtu
- -
05 2.1222: Install turbulators $370 $800 - - $370
-
MMBtu
- -
06 2.2414: Use waste heat from hot flue gases to preheat $314 $1,000 - - $314
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $258 $235 $155
2,345
kWh
$7
-
kW-mo/yr
- $96 -
08 4.521: Clear and rent existing space $54,000 $1,000 - - - - $54,000
09 4.111: Add equipment/ operators to reduce production bottleneck $26,555 $5,000 - - - $26,555 -
10 4.441: Install automatic packing equipment $1,560 $1,300 - - - - $1,560
TOTAL RECOMMENDED $87,351 $16,110 $3,335
50,118
kWh
$628
-
kW-mo/yr
$1,177
-
MMBtu
$26,651 $55,560
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs