ITAC Assessment: BD0171
ITAC logo
ITAC Assessment: BD0171
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Zinc and Aluminum Die Castings
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area 32,500
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 4,680
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,148 1,790,739
kWh
Electricity Demand $70,823 6,154
kW-mo/yr
Electricity Fees $986 -
Natural Gas $105,645 34,662
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $914,536 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,190

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings Increase in Production Savings
01 2.4133: Use most efficient type of electric motors $4,759 $9,930 $3,129
215,785
kWh
$1,630
-
kW-mo/yr
- - - - - - - -
02 2.6218: Turn off equipment when not in use $1,506 $500 $1,506
103,842
kWh
- - - - - - - - -
03 2.7135: Install occupancy sensors $1,317 $1,050 $617
42,509
kWh
$700
-
kW-mo/yr
- - - - - - - -
04 2.4314: Use synthetic lubricant $1,003 $700 $388
26,747
kWh
$615
-
kW-mo/yr
- - - - - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $767 $600 $294
20,340
kWh
$473
-
kW-mo/yr
- - - - - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $398 $324 $170
11,707
kWh
$63
-
kW-mo/yr
- - - - - $165 - -
07 2.2514: Cover open tanks $206 $470 - - $206
-
MMBtu
- - - - - - -
08 3.7198: Reduce / eliminate use of disposable product $39,357 $4,000 - - - - $54,000
-
lb
- $(-14,643.0) - - -
09 3.4151: Minimize water usage $209 $805 - - - $209
-
Tgal
- - - - - -
10 4.111: Add equipment/ operators to reduce production bottleneck $863,728 $550,000 - - - - - - $(-409,000.0) - - $1,272,728
11 4.441: Install automatic packing equipment $936 $1,400 - - - - - - - - $936 -
12 3.5316: Contract a wood pallet recycling company $350 $200 - - - - - $350
-
lb
- - - -
TOTAL RECOMMENDED $914,536 $569,979 $6,104
420,930
kWh
$3,481
-
kW-mo/yr
$206
-
MMBtu
$209
-
Tgal
$54,000
-
lb
$350
-
lb
$(-423,643.0) $165 $936 $1,272,728
TOTAL IMPLEMENTED $43,190 $8,649 $1,081
74,556
kWh
$1,236
-
kW-mo/yr
$206
-
MMBtu
$209
-
Tgal
$54,000
-
lb
- $(-14,643.0) $165 $936 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs