ITAC Assessment: SF0590
ITAC logo
ITAC Assessment: SF0590
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Treated Water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area 958,320
ft2
Annual Production 6,200,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $282,469 2,652,856
kWh
Electricity Demand $316,992 14,124
kW-mo/yr
Natural Gas $278,217 40,607
MMBtu
TOTAL YEARLY COSTS $877,678
RECOMMENDED SAVINGS* $263,554 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $212,797

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $79,227 $13,234 $61,476
577,237
kWh
$17,751
-
kW-mo/yr
-
02 2.4322: Use or replace with energy efficient substitutes $38,848 $11,000 $5,687
53,403
kWh
$25,673
-
kW-mo/yr
$7,488
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $65,729 $89,990 $54,119
508,161
kWh
$11,610
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,777 $19,007 $6,777
63,630
kWh
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,909 $34,177 $11,909
111,825
kWh
- -
06 2.9114: Use solar heat to make electricty $61,064 $434,923 $61,064
573,367
kWh
- -
TOTAL RECOMMENDED $263,554 $602,331 $201,032
1,887,623
kWh
$55,034
-
kW-mo/yr
$7,488
TOTAL IMPLEMENTED $212,797 $557,154 $183,436
1,722,395
kWh
$29,361
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs