Assessment Year | 2000 |
---|---|
Principal Product | Specialty Cutting Tools |
NAICS |
n/a
|
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
25,000
ft2
|
Annual Production | 16,000
lb
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $23,763 | 483,880 |
kWh
|
$0.049 |
Electricity Demand | $26,293 | 2,116 |
kW-mo/yr
|
$12.43 |
Electricity Fees | $292 | - |
|
- |
Natural Gas | $3,223 | 552 |
MMBtu
|
$5.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $277,304 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,161 | $500 | n/a |
$636
12,896
kWh
|
$525
-
kW-mo/yr
|
- | - |
02 | 2.6218: Turn off equipment when not in use | $776 | $1,750 | n/a |
$317
6,448
kWh
|
$459
-
kW-mo/yr
|
- | - |
03 | 2.7135: Install occupancy sensors | $529 | $600 | n/a |
$259
5,275
kWh
|
$270
-
kW-mo/yr
|
- | - |
04 | 3.3131: Use evaporation to concentrate material | $924 | $3,400 | n/a | - | - |
$924
-
Tgal
|
- |
05 | 3.4151: Minimize water usage | $328 | $1,080 | n/a | - | - |
$328
-
Tgal
|
- |
06 | 4.515: Install shelves / racks to utilize unused space | $273,586 | $375,000 | n/a | - | - | - | $273,586 |
TOTAL RECOMMENDED | $277,304 | $382,330 |
$1,212
24,619
kWh
|
$1,254
-
kW-mo/yr
|
$1,252
-
Tgal
|
$273,586 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs