| Assessment Year | 2000 |
|---|---|
| Principal Product | Sodium Erythorbate |
| NAICS |
n/a
|
| SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 53 |
| Plant Area |
117,480
ft2
|
| Annual Production | 8,800,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $423,808 | 15,036,049 |
kWh
|
$0.028 |
| Electricity Demand | $255,710 | 17,460 |
kW-mo/yr
|
$14.65 |
| Electricity Fees | $26,645 | - |
|
- |
| Natural Gas | $843,755 | 276,457 |
MMBtu
|
$3.05 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $46,710 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,863 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $23,362 | $15,000 | - | - |
$23,362
-
MMBtu
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $14,902 | $19,530 |
$9,705
344,080
kWh
|
$5,197
-
kW-mo/yr
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $3,077 | $2,400 |
$1,561
55,393
kWh
|
$1,516
-
kW-mo/yr
|
- | - | |
| 04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,226 | $8,000 | - | - | - |
$3,226
-
lb
|
|
| 05 | 3.5241: Sell used plates to an aluminum recycler | $1,863 | $600 | - | - | - |
$1,863
-
lb
|
|
| 06 | 3.5316: Contract a wood pallet recycling company | $280 | $600 | - | - | - |
$280
-
lb
|
|
| TOTAL RECOMMENDED | $46,710 | $46,130 |
$11,266
399,473
kWh
|
$6,713
-
kW-mo/yr
|
$23,362
-
MMBtu
|
$5,369
-
lb
|
||
| TOTAL IMPLEMENTED | $1,863 | $600 | - | - | - |
$1,863
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs