Assessment Year | 2000 |
---|---|
Principal Product | Sodium Erythorbate |
NAICS |
n/a
|
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 53 |
Plant Area |
117,480
ft2
|
Annual Production | 8,800,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $423,808 | 15,036,049 |
kWh
|
$0.028 |
Electricity Demand | $255,710 | 17,460 |
kW-mo/yr
|
$14.65 |
Electricity Fees | $26,645 | - |
|
- |
Natural Gas | $843,755 | 276,457 |
MMBtu
|
$3.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,710 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,863 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $23,362 | $15,000 | - | - |
$23,362
-
MMBtu
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $14,902 | $19,530 |
$9,705
344,080
kWh
|
$5,197
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $3,077 | $2,400 |
$1,561
55,393
kWh
|
$1,516
-
kW-mo/yr
|
- | - | |
04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,226 | $8,000 | - | - | - |
$3,226
-
lb
|
|
05 | 3.5241: Sell used plates to an aluminum recycler | $1,863 | $600 | - | - | - |
$1,863
-
lb
|
|
06 | 3.5316: Contract a wood pallet recycling company | $280 | $600 | - | - | - |
$280
-
lb
|
|
TOTAL RECOMMENDED | $46,710 | $46,130 |
$11,266
399,473
kWh
|
$6,713
-
kW-mo/yr
|
$23,362
-
MMBtu
|
$5,369
-
lb
|
||
TOTAL IMPLEMENTED | $1,863 | $600 | - | - | - |
$1,863
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs