Assessment Year | 2000 |
---|---|
Principal Product | Roof bolts and Plates |
NAICS |
n/a
|
SIC | 2439: Structural Wood Members, Not Elsewhere Classified |
Sales Range | n/a |
# of Employees | 100 |
Plant Area |
60,000
ft2
|
Annual Production | 800,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,698 | 1,917,351 |
kWh
|
$0.034 |
Electricity Demand | $74,488 | 6,457 |
kW-mo/yr
|
$11.54 |
Electricity Fees | $1,495 | - |
|
- |
Natural Gas | $214,342 | 32,556 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,818 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,670 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,576 | $1,000 |
$3,362
99,648
kWh
|
$2,214
-
kW-mo/yr
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $4,094 | $1,000 |
$4,094
364,596
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,375 | $260 |
$827
24,619
kWh
|
$548
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $1,042 | $600 |
$613
18,171
kWh
|
$429
-
kW-mo/yr
|
- | - | |
05 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $9,000 | $1,000 | - | - |
$9,000
-
lb
|
- | |
06 | 4.441: Install automatic packing equipment | $7,201 | $4,500 | - | - | - | $7,201 | |
07 | 4.821: Pay bills on time to avoid late fees | $530 | - | - | - | - | $530 | |
TOTAL RECOMMENDED | $28,818 | $8,360 |
$8,896
507,034
kWh
|
$3,191
-
kW-mo/yr
|
$9,000
-
lb
|
$7,731 | ||
TOTAL IMPLEMENTED | $18,670 | $3,000 |
$7,456
464,244
kWh
|
$2,214
-
kW-mo/yr
|
$9,000
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs