ITAC Assessment: BD0151
ITAC logo
ITAC Assessment: BD0151
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Industrial Marking Equipment & Inks
NAICS
n/a
SIC 3953: Marking Devices
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 110,000
ft2
Annual Production 25,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,252 813,599
kWh
Electricity Demand $39,411 3,363
kW-mo/yr
Electricity Fees $960 -
Natural Gas $31,745 8,070
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,245 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Increase in Production Savings
01 2.1221: Replace obsolete burners with more efficient ones $6,104 $20,000 - - $6,104
-
MMBtu
- -
02 2.7135: Install occupancy sensors $5,699 $3,075 $3,829
65,944
kWh
$1,870
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,828 - $1,432
24,619
kWh
$396
-
kW-mo/yr
- - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,720 $3,000 $1,360
23,447
kWh
$1,360
-
kW-mo/yr
- - -
05 2.4133: Use most efficient type of electric motors $781 $1,320 $604
10,551
kWh
$177
-
kW-mo/yr
- - -
06 3.5112: Reprocess spent oils on site for re-use $1,181 $800 - - - $1,181
-
gal
-
07 4.441: Install automatic packing equipment $1,932 $8,000 - - - - $1,932
TOTAL RECOMMENDED $20,245 $36,195 $7,225
124,561
kWh
$3,803
-
kW-mo/yr
$6,104
-
MMBtu
$1,181
-
gal
$1,932
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs