Assessment Year | 2000 |
---|---|
Principal Product | Industrial Marking Equipment & Inks |
NAICS |
n/a
|
SIC | 3953: Marking Devices |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
110,000
ft2
|
Annual Production | 25,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,252 | 813,599 |
kWh
|
$0.058 |
Electricity Demand | $39,411 | 3,363 |
kW-mo/yr
|
$11.72 |
Electricity Fees | $960 | - |
|
- |
Natural Gas | $31,745 | 8,070 |
MMBtu
|
$3.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1221: Replace obsolete burners with more efficient ones | $6,104 | $20,000 | - | - |
$6,104
-
MMBtu
|
- | - | |
02 | 2.7135: Install occupancy sensors | $5,699 | $3,075 |
$3,829
65,944
kWh
|
$1,870
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,828 | - |
$1,432
24,619
kWh
|
$396
-
kW-mo/yr
|
- | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,720 | $3,000 |
$1,360
23,447
kWh
|
$1,360
-
kW-mo/yr
|
- | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $781 | $1,320 |
$604
10,551
kWh
|
$177
-
kW-mo/yr
|
- | - | - | |
06 | 3.5112: Reprocess spent oils on site for re-use | $1,181 | $800 | - | - | - |
$1,181
-
gal
|
- | |
07 | 4.441: Install automatic packing equipment | $1,932 | $8,000 | - | - | - | - | $1,932 | |
TOTAL RECOMMENDED | $20,245 | $36,195 |
$7,225
124,561
kWh
|
$3,803
-
kW-mo/yr
|
$6,104
-
MMBtu
|
$1,181
-
gal
|
$1,932 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs