ITAC Assessment: BD0132
ITAC logo
ITAC Assessment: BD0132
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Turbine Engine Components
NAICS
n/a
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $10
M
to 50
M
# of Employees 465
Plant Area 177,600
ft2
Annual Production 3,500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $371,622 9,557,444
kWh
Electricity Demand $231,426 19,838
kW-mo/yr
Electricity Fees $13,230 -
Natural Gas $31,659 6,800
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $58,010 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,941

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,002 $27,440 $6,977
179,367
kWh
$4,025
-
kW-mo/yr
- - - -
02 2.7135: Install occupancy sensors $2,901 $1,050 $1,845
47,479
kWh
$1,056
-
kW-mo/yr
- - - -
03 2.4133: Use most efficient type of electric motors $2,923 $8,000 $2,252
58,030
kWh
$671
-
kW-mo/yr
- - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,514 $4,000 $2,913
75,029
kWh
$1,008
-
kW-mo/yr
$(-1,407.0)
-
MMBtu
- - -
05 2.7231: Use radiant heater for spot heating $1,339 $1,600 $254
6,448
kWh
$74
-
kW-mo/yr
$1,011
-
MMBtu
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $707 $900 $385
9,965
kWh
$322
-
kW-mo/yr
- - - -
07 3.4111: Use closed cycle process to minimize waste water production $2,232 $4,200 - - - $2,232
-
Tgal
- -
08 3.5315: Lease / purchase baler; sell cardboard to recycler $2,217 $7,000 - - - - $2,217
-
lb
-
09 3.4151: Minimize water usage $1,215 $3,125 - - - $1,215
-
Tgal
- -
10 4.445: Install equipment to move product $30,960 $50,000 - - - - - $30,960
TOTAL RECOMMENDED $58,010 $107,315 $14,626
376,318
kWh
$7,156
-
kW-mo/yr
$(-396.0)
-
MMBtu
$3,447
-
Tgal
$2,217
-
lb
$30,960
TOTAL IMPLEMENTED $13,941 $32,540 $7,362
189,332
kWh
$4,347
-
kW-mo/yr
- $2,232
-
Tgal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs