Assessment Year | 1999 |
---|---|
Principal Product | Printed Paper |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
40,000
ft2
|
Annual Production | 5,100,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,273 | 1,324,150 |
kWh
|
$0.046 |
Electricity Demand | $47,459 | 3,774 |
kW-mo/yr
|
$12.58 |
Electricity Fees | $1,279 | - |
|
- |
Natural Gas | $7,482 | 1,558 |
MMBtu
|
$4.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,306 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,375 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $4,723 | $500 | - | - |
$4,723
-
MMBtu
|
- | - | |
02 | 2.7231: Use radiant heater for spot heating | $3,506 | $2,000 |
$1,270
30,188
kWh
|
$423
-
kW-mo/yr
|
$1,813
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $807 | $646 |
$495
11,723
kWh
|
$312
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $1,466 | $2,040 |
$1,068
25,498
kWh
|
$398
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,416 | $1,614 |
$929
22,274
kWh
|
$487
-
kW-mo/yr
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $867 | $450 |
$571
13,775
kWh
|
$296
-
kW-mo/yr
|
- | - | - | |
07 | 3.4115: Recover and reuse cooling water | $1,453 | $2,410 | - | - | - |
$1,453
-
Tgal
|
- | |
08 | 4.444: Install system to collect scrap | $22,068 | $8,700 | - | - | - | - | $22,068 | |
TOTAL RECOMMENDED | $36,306 | $18,360 |
$4,333
103,458
kWh
|
$1,916
-
kW-mo/yr
|
$6,536
-
MMBtu
|
$1,453
-
Tgal
|
$22,068 | ||
TOTAL IMPLEMENTED | $6,375 | $6,024 |
$2,199
52,462
kWh
|
$910
-
kW-mo/yr
|
$1,813
-
MMBtu
|
$1,453
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs