ITAC Assessment: BD0126
ITAC logo
ITAC Assessment: BD0126
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Zinc Die Cast Parts
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $50
M
to 100
M
# of Employees 490
Plant Area 194,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $320,189 8,670,575
kWh
Electricity Demand $230,959 16,489
kW-mo/yr
Electricity Fees $10,629 -
Natural Gas $272,762 90,150
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $104,136 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $70,664

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings One-time Revenue or Avoided Cost Savings
01 2.1221: Replace obsolete burners with more efficient ones $25,827 $78,000 - - $25,827
-
MMBtu
- - -
02 2.4133: Use most efficient type of electric motors $25,009 $31,450 $15,315
415,006
kWh
$9,694
-
kW-mo/yr
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,739 $3,302 $4,778
129,543
kWh
$2,961
-
kW-mo/yr
- - - -
04 2.7135: Install occupancy sensors $7,645 $2,700 $5,016
135,991
kWh
$2,629
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,658 $1,125 $2,896
78,546
kWh
$1,762
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,785 $2,365 $1,110
30,188
kWh
$675
-
kW-mo/yr
- - - -
07 3.4114: Replace city water with recycled water via cooling tower $16,941 $14,000 - - - $16,941
-
Tgal
- -
08 3.3131: Use evaporation to concentrate material $8,527 $5,500 - - - - $8,527
-
gal
-
09 4.131: Modify process to reduce material use/cost $6,005 $1,500 - - - - - $6,005
TOTAL RECOMMENDED $104,136 $139,942 $29,115
789,274
kWh
$17,721
-
kW-mo/yr
$25,827
-
MMBtu
$16,941
-
Tgal
$8,527
-
gal
$6,005
TOTAL IMPLEMENTED $70,664 $59,242 $24,099
653,283
kWh
$15,092
-
kW-mo/yr
- $16,941
-
Tgal
$8,527
-
gal
$6,005
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs