ITAC Assessment: BD0119
ITAC logo
ITAC Assessment: BD0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Steel Doors and Frames
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 109,845
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 3,744
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $123,608 1,328,546
kWh
Electricity Demand $57,136 4,535
kW-mo/yr
Electricity Fees $2,585 -
Natural Gas $114,651 20,983
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $192,107 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.1221: Replace obsolete burners with more efficient ones $23,453 $10,000 n/a - - $23,453
-
MMBtu
- - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,670 $4,000 n/a $1,843
45,721
kWh
$2,948
-
kW-mo/yr
$(-1,121.0)
-
MMBtu
- - - -
03 2.4133: Use most efficient type of electric motors $1,663 $3,460 n/a $1,062
26,377
kWh
$601
-
kW-mo/yr
- - - - -
04 2.4221: Install compressor air intakes in coolest locations $1,434 $400 n/a $755
18,757
kWh
$679
-
kW-mo/yr
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,178 $3,835 n/a $535
13,189
kWh
$643
-
kW-mo/yr
- - - - -
06 2.7135: Install occupancy sensors $1,158 $600 n/a $628
15,533
kWh
$530
-
kW-mo/yr
- - - - -
07 2.2515: Use optimum thickness insulation $1,125 $1,515 n/a - - $1,125
-
MMBtu
- - - -
08 2.2515: Use optimum thickness insulation $549 $2,127 n/a - - $549
-
MMBtu
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $382 $430 n/a $198
4,982
kWh
$184
-
kW-mo/yr
- - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $230 $205 n/a $94
2,345
kWh
$40
-
kW-mo/yr
- - - - $96
11 3.2123: Convert to high volume low pressure (hvlp) paint guns $132,757 $160,000 n/a - - - - $18,000
-
gal
$(-1,808.0) $116,565
12 3.2123: Convert to high volume low pressure (hvlp) paint guns $13,430 $14,000 n/a - - - - - - $13,430
13 3.5311: Recover and reuse waste material $2,982 $7,000 n/a - - - $2,982
-
Tgal
- - -
14 4.423: Move product using mechanical means $4,359 $14,000 n/a - - $(-154.0)
-
MMBtu
- - $4,513 -
15 4.652: Replace existing equipment with more suitable substitutes $3,737 $1,365 n/a - - - - - $3,737 -
TOTAL RECOMMENDED $192,107 $222,937 $5,115
126,904
kWh
$5,625
-
kW-mo/yr
$23,852
-
MMBtu
$2,982
-
Tgal
$18,000
-
gal
$6,442 $130,091
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs