Assessment Year | 1998 |
---|---|
Principal Product | Automotive Body Support Components |
NAICS |
n/a
|
SIC | 3465: Automotive Stampings |
Sales Range | $50 M to 100M |
# of Employees | 468 |
Plant Area |
330,000
ft2
|
Annual Production | 192,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $284,606 | 11,276,085 |
kWh
|
$0.025 |
Electricity Demand | $321,419 | 28,038 |
kW-mo/yr
|
$11.46 |
Natural Gas | $169,828 | 48,717 |
MMBtu
|
$3.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,584 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,475 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $13,739 | $20,000 | - | - |
$13,739
-
MMBtu
|
- | |
02 | 2.1213: Direct warmest air to combustion intake | $7,819 | $12,000 | - | - |
$7,819
-
MMBtu
|
- | |
03 | 2.3192: Use fossil fuel powered generator during peak demand periods | $5,674 | $1,000 |
$2,523
100,234
kWh
|
$7,564
-
kW-mo/yr
|
$(-3,913.0)
-
MMBtu
|
$(-500.0) | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,657 | $5,900 |
$2,261
89,683
kWh
|
$1,977
-
kW-mo/yr
|
- | $419 | |
05 | 2.4221: Install compressor air intakes in coolest locations | $3,961 | $1,000 |
$2,028
80,598
kWh
|
$1,933
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $1,062 | $900 |
$553
21,981
kWh
|
$509
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $300 | $335 |
$92
3,810
kWh
|
$57
-
kW-mo/yr
|
- | $151 | |
08 | 2.7134: Use photocell controls | $206 | $200 |
$72
2,931
kWh
|
$125
-
kW-mo/yr
|
- | $9 | |
09 | 3.5316: Contract a wood pallet recycling company | $3,796 | $320 | - | - | - | $3,796 | |
10 | 4.652: Replace existing equipment with more suitable substitutes | $12,370 | $12,500 | - | - |
$(-100.0)
-
MMBtu
|
$12,470 | |
TOTAL RECOMMENDED | $53,584 | $54,155 |
$7,529
299,237
kWh
|
$12,165
-
kW-mo/yr
|
$17,545
-
MMBtu
|
$16,345 | ||
TOTAL IMPLEMENTED | $27,475 | $21,655 |
$7,529
299,237
kWh
|
$12,165
-
kW-mo/yr
|
$3,906
-
MMBtu
|
$3,875 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs