| Assessment Year | 1998 |
|---|---|
| Principal Product | Polystyrene Cups & Lids |
| NAICS |
n/a
|
| SIC | 3086: Plastics Foam Products |
| Sales Range | $10 M to 50M |
| # of Employees | 149 |
| Plant Area |
284,636
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $878,222 | 21,451,642 |
kWh
|
$0.041 |
| Electricity Demand | $468,142 | 33,303 |
kW-mo/yr
|
$14.06 |
| Electricity Fees | $6,865 | - |
|
- |
| Natural Gas | $1,104,418 | 358,760 |
MMBtu
|
$3.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $231,695 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $59,224 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1222: Install turbulators | $28,680 | $1,650 | - | - |
$28,680
-
MMBtu
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $26,005 | $40,190 |
$19,213
469,812
kWh
|
$6,792
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1123: Install automatic stack damper | $6,809 | $2,100 | - | - |
$6,809
-
MMBtu
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,851 | $3,986 |
$2,307
56,565
kWh
|
$1,544
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 3.4157: Replace water cooling on processes with air cooling | $32,510 | $128,700 |
$(-1,558.0)
(-38,101)
kWh
|
$(-612.0)
-
kW-mo/yr
|
- | - | - | $34,680 | |
| 06 | 3.4151: Minimize water usage | $688 | $1,625 | - | - | - |
$688
-
Tgal
|
- | - | |
| 07 | 4.441: Install automatic packing equipment | $133,152 | $72,000 | - | - | - | - | $133,152 | - | |
| TOTAL RECOMMENDED | $231,695 | $250,251 |
$19,962
488,276
kWh
|
$7,724
-
kW-mo/yr
|
$35,489
-
MMBtu
|
$688
-
Tgal
|
$133,152 | $34,680 | ||
| TOTAL IMPLEMENTED | $59,224 | $47,451 |
$21,520
526,377
kWh
|
$8,336
-
kW-mo/yr
|
$28,680
-
MMBtu
|
$688
-
Tgal
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs