Assessment Year | 1997 |
---|---|
Principal Product | Fuses and Fuse Components |
NAICS |
n/a
|
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
25,000
ft2
|
Annual Production | 38,000,000
pieces
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,613 | 1,109,320 |
kWh
|
$0.032 |
Electricity Demand | $37,865 | 3,249 |
kW-mo/yr
|
$11.65 |
Electricity Fees | $4,056 | - |
|
- |
Natural Gas | $7,798 | 1,692 |
MMBtu
|
$4.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $588,998 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $545,409 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $2,363 | $700 | - | - |
$2,363
-
MMBtu
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $996 | $300 |
$445
13,775
kWh
|
$551
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $993 | - |
$993
31,067
kWh
|
- | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $854 | $450 |
$854
26,671
kWh
|
- | - | - | - | - | |
05 | 3.4151: Minimize water usage | $792 | $1,240 | - | - | - | - | - |
$792
-
Tgal
|
|
06 | 3.5316: Contract a wood pallet recycling company | $600 | $300 | - | - | - | - | $600 | - | |
07 | 4.452: Eliminate shift | $291,200 | $120,000 | - | - | - | $291,200 | - | - | |
08 | 4.452: Eliminate shift | $249,600 | $120,000 | - | - | - | $249,600 | - | - | |
09 | 4.452: Eliminate shift | $41,600 | $40,000 | - | - | - | $41,600 | - | - | |
TOTAL RECOMMENDED | $588,998 | $282,990 |
$2,292
71,513
kWh
|
$551
-
kW-mo/yr
|
$2,363
-
MMBtu
|
$582,400 | $600 |
$792
-
Tgal
|
||
TOTAL IMPLEMENTED | $545,409 | $242,690 |
$854
26,671
kWh
|
- |
$2,363
-
MMBtu
|
$540,800 | $600 |
$792
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs