Assessment Year | 1997 |
---|---|
Principal Product | Reconditioned Steel Drums |
NAICS |
n/a
|
SIC | 3412: Metal Shipping Barrels, Drums, Kegs, and Pails |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
80,000
ft2
|
Annual Production | 1,483,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $152,953 | 3,247,362 |
kWh
|
$0.047 |
Electricity Demand | $193,497 | 12,680 |
kW-mo/yr
|
$15.26 |
Electricity Fees | $7,300 | - |
|
- |
Natural Gas | $315,603 | 100,543 |
MMBtu
|
$3.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $384,718 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $367,280 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $8,910 | $1,500 | - | - |
$8,910
-
MMBtu
|
- | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,630 | $5,699 |
$3,051
64,771
kWh
|
$4,579
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.2511: Insulate bare equipment | $4,842 | $8,668 | - | - |
$4,842
-
MMBtu
|
- | - | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $2,560 | $4,430 |
$1,068
22,567
kWh
|
$1,492
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.7135: Install occupancy sensors | $898 | $1,050 |
$346
7,327
kWh
|
$552
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $192,343 | $16,000 | - | - | - | - |
$2,938
-
gal
|
- | $189,405 | - | - | |
07 | 3.4113: Treat and reuse rinse waters | $16,735 | $34,000 | - | - | - |
$52,000
-
Tgal
|
$(-32,500.0)
-
gal
|
$(-2,899.0) | - |
$134
-
Tgal
|
- | |
08 | 4.122: Develop standard procedures to improve internal yields | $150,800 | $2,000 | - | - | - | - | - | - | - | - | $150,800 | |
TOTAL RECOMMENDED | $384,718 | $73,347 |
$4,465
94,665
kWh
|
$6,623
-
kW-mo/yr
|
$13,752
-
MMBtu
|
$52,000
-
Tgal
|
$(-29,562.0)
-
gal
|
$(-2,899.0) | $189,405 |
$134
-
Tgal
|
$150,800 | ||
TOTAL IMPLEMENTED | $367,280 | $65,098 |
$1,068
22,567
kWh
|
$1,492
-
kW-mo/yr
|
$4,842
-
MMBtu
|
$52,000
-
Tgal
|
$(-29,562.0)
-
gal
|
$(-2,899.0) | $189,405 |
$134
-
Tgal
|
$150,800 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs