Assessment Year | 1997 |
---|---|
Principal Product | Machine Tool Protection Equipment |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
57,500
ft2
|
Annual Production | 5,300
pieces
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,983 | 732,122 |
kWh
|
$0.038 |
Electricity Demand | $30,998 | 2,512 |
kW-mo/yr
|
$12.34 |
Electricity Fees | $2,839 | - |
|
- |
Natural Gas | $11,401 | 2,932 |
MMBtu
|
$3.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,672 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,412 | $2,845 | - | - |
$2,412
-
MMBtu
|
- | - | - | |
02 | 2.6218: Turn off equipment when not in use | $1,569 | $1,500 | - | - |
$1,569
-
MMBtu
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,196 | $520 |
$1,196
36,342
kWh
|
- | - | - | - | - | |
04 | 2.7135: Install occupancy sensors | $1,024 | $750 |
$397
12,016
kWh
|
$627
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7496: Install partitions to reduce size of conditioned space | $904 | $750 | - | - |
$904
-
MMBtu
|
- | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $859 | $2,750 |
$393
12,016
kWh
|
$466
-
kW-mo/yr
|
- | - | - | - | |
07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $12,554 | $14,000 | - | - | - | - | $7,708 | $4,846 | |
08 | 3.7131: Use a rag recycle service | $1,404 | - | - | - | - | - | - | $1,404 | |
09 | 4.445: Install equipment to move product | $18,750 | $4,000 | - | - | - | $18,750 | - | - | |
TOTAL RECOMMENDED | $40,672 | $27,115 |
$1,986
60,374
kWh
|
$1,093
-
kW-mo/yr
|
$4,885
-
MMBtu
|
$18,750 | $7,708 | $6,250 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs