| Assessment Year | 1996 |
|---|---|
| Principal Product | Commercial Cleaning Equipment |
| NAICS |
n/a
|
| SIC | 3698: |
| Sales Range | $50 M to 100M |
| # of Employees | 100 |
| Plant Area |
112,000
ft2
|
| Annual Production | 50,000
pieces
|
| Production Hrs. Annual | 4,550
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,882 | 1,665,592 |
kWh
|
$0.037 |
| Electricity Demand | $64,512 | 5,281 |
kW-mo/yr
|
$12.22 |
| Electricity Fees | $701 | - |
|
- |
| Natural Gas | $44,416 | 13,555 |
MMBtu
|
$3.28 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,936 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,396 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $5,002 | $3,225 |
$2,708
77,960
kWh
|
$2,294
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $4,228 | $4,228 |
$2,495
71,805
kWh
|
$1,733
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $2,652 | $2,000 |
$2,652
76,202
kWh
|
- | - | - | - | |
| 04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,520 | $1,950 | - | - |
$2,520
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,744 | $3,591 |
$887
25,498
kWh
|
$857
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $631 | $400 |
$631
18,171
kWh
|
- | - | - | - | |
| 07 | 3.4115: Recover and reuse cooling water | $2,159 | $3,500 | - | - | - | $(-500.0) |
$2,659
-
Tgal
|
|
| TOTAL RECOMMENDED | $18,936 | $18,894 |
$9,373
269,636
kWh
|
$4,884
-
kW-mo/yr
|
$2,520
-
MMBtu
|
$(-500.0) |
$2,659
-
Tgal
|
||
| TOTAL IMPLEMENTED | $4,396 | $5,591 |
$3,539
101,700
kWh
|
$857
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs