ITAC Assessment: AT0111
ITAC logo
ITAC Assessment: AT0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product DIARY PRODUCTS
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area
n/a
Annual Production 7,000,000
lb
Production Hrs. Annual 4,992
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $141,153 2,358,441
kWh
Natural Gas $135,033 39,228
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,524 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,733

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $39,530 $60,000 - $39,530
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $715 - - $1,015
-
MMBtu
$(-300.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,057 $175 $1,057
17,585
kWh
- -
04 2.4133: Use most efficient type of electric motors $710 $665 $710
12,016
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,251 - $1,251
20,809
kWh
- -
06 2.4312: Improve lubrication practices $261 - $261
4,396
kWh
- -
TOTAL RECOMMENDED $43,524 $60,840 $3,279
54,806
kWh
$40,545
-
MMBtu
$(-300.0)
TOTAL IMPLEMENTED $3,733 $840 $3,018
50,410
kWh
$1,015
-
MMBtu
$(-300.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs