ITAC Assessment: AT0091
ITAC logo
ITAC Assessment: AT0091
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product POT HOLDERS, APRONS,BAGS
NAICS
n/a
SIC 2399: Fabricated Textile Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 0
Plant Area
n/a
Annual Production 3,000,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,272 686,108
kWh
Natural Gas $1,741 278
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,166 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,682

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7226: Use computer programs to optimize hvac performance $2,727 $7,500 $2,727
41,325
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $793 $264 $793
12,016
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $162 - $162
2,345
kWh
04 2.2522: Isolate hot or cold equipment $484 $200 $484
7,327
kWh
TOTAL RECOMMENDED $4,166 $7,964 $4,166
63,013
kWh
TOTAL IMPLEMENTED $3,682 $7,764 $3,682
55,686
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs