ITAC Assessment: AT0070
ITAC logo
ITAC Assessment: AT0070
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product SASHES & WEATHER STRIPS
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $5
M
to 10
M
# of Employees 74
Plant Area
n/a
Annual Production 5,000
ton
Production Hrs. Annual 6,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,028 781,946
kWh
Natural Gas $15,604 2,000
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,382 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,612

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2614: Use cooling tower or economizer to replace chiller cooling $1,770 $2,500 $1,770
30,188
kWh
- -
02 2.4133: Use most efficient type of electric motors $414 $298 $414
7,034
kWh
- -
03 2.4312: Improve lubrication practices $4,158 - $5,058
85,873
kWh
- $(-900.0)
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $361 - $361
6,155
kWh
- -
05 2.2437: Recover waste heat from equipment $679 $300 - $679
-
MMBtu
-
TOTAL RECOMMENDED $7,382 $3,098 $7,603
129,250
kWh
$679
-
MMBtu
$(-900.0)
TOTAL IMPLEMENTED $5,612 $598 $5,833
99,062
kWh
$679
-
MMBtu
$(-900.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs