ITAC Assessment: AT0067
ITAC logo
ITAC Assessment: AT0067
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product WOMENS UNDERGARMENTS
NAICS
n/a
SIC 2341: Women's, Misses', Children's, and Infants' Underwear and Nightwear
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 2,400,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,278 1,065,064
kWh
Natural Gas $4,891 726
MMBtu
Coal $7,493 2,363
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,249 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,669

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,141 $481 $1,141
17,292
kWh
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $580 $1,500 $1,025
15,533
kWh
$(-445.0)
-
MMBtu
03 2.7226: Use computer programs to optimize hvac performance $1,199 $1,000 $1,199
18,171
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $174 $50 $174
2,638
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $155 - $155
2,345
kWh
-
TOTAL RECOMMENDED $3,249 $3,031 $3,694
55,979
kWh
$(-445.0)
-
MMBtu
TOTAL IMPLEMENTED $2,669 $1,531 $2,669
40,446
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs