ITAC Assessment: AT0024
ITAC logo
ITAC Assessment: AT0024
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product FURNITURE
NAICS
n/a
SIC 2512: Wood Household Furniture, Upholstered
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area
n/a
Annual Production 15,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,664 376,026
kWh
Natural Gas $4,926 760
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,398 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $111

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $29 $70 $29
293
kWh
02 2.4231: Reduce the pressure of compressed air to the minimum required $111 - $111
1,758
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $187 $162 $187
2,931
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,357 $407 $1,357
21,688
kWh
05 2.7226: Use computer programs to optimize hvac performance $2,714 $5,400 $2,714
43,083
kWh
TOTAL RECOMMENDED $4,398 $6,039 $4,398
69,753
kWh
TOTAL IMPLEMENTED $111 - $111
1,758
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs